Some road closings and detours are required during the construction work.

Work to be completed in the week of Nov. 12-16:

  • Feriozzi Concrete will finish work on Seventh Street between West Avenue and Bay Avenue, restoring curb, gutter and sidewalks. The contractor then will begin restoration work on Haven Avenue between Seventh Street and Eighth Street.
  • Pipe crews will continue work between First Street and Second Street on West Avenue installing a main. At the same time, a second crew will install a main on Bay Avenue between Second Street and Third Street.
  • Sodding will continue on Fourth and Fifth Street.

Project design:

See Design Presentation for Detail