Home Latest Stories Bay Avenue Construction Update

Bay Avenue Construction Update

2310
SHARE
Detour signs were a common sight on Bay Avenue during construction.

The Cape May County Municipal Utilities Authority is replacing and rehabilitating the force mains that carry wastewater to the treatment plant on the bay at 45th Street. The work is being done on 31st Street from Haven Avenue to Bay Avenue and Bay Avenue from 31st Street to Eighth Street.

Currently, the contractor’s efforts are focused on the stretch of work between 10th and 11th Streets. This is the remaining segment where new 20-inch PVC pipe needs to be installed. As a result of the concentration of manpower, materials and equipment in the 12th through Ninth Street work zone, the installation of temporary pavement in this area has been suspended.

Other work that is scheduled to be done this week includes the installation of the valve vault on the property of the Municipal Utilities Authority’s 20th Street Pump Station, with related pipe tie-in work and the installation of vent piping that serves the concrete chambers that are distributed throughout the length of the project. Neither of these tasks will require traffic shutdowns. Traffic control will be handled with lane shifts.

Looking out longer term, it is expected that the new 20-inch PVC pipe will become operable by about mid-April, 2020. At that time, the slip-lining (of the existing DIP force main) phase of the project will begin.

It is expected that the slip-lining work will extend to mid-June, 2020. It is not expected that large traffic detours will be required during the slip-lining phase of work. Traffic control will be handled via lane shifts then.

See full project update