Third Street awaits a new layer of paving.
Work to be completed in the week of Oct. 1-5:
·
Feriozzi Concrete will continue work on Sixth Street between West Avenue and Bay Avenue restoring curb gutter and sidewalks.
·
Pipe crews will continue installing main on Seventh Street, working from Bay Avenue to West Avenue.
·
Paving crews will continue paving from Second Street to Fifth Street between West Avenue and Bay Avenue.
·
Mayor Jay Gillian said the contractor paved Fifth Street this week. The completion of Fifth Street comes in time for Saturday’s Bike MS: City to Shore Ride, which ends on Fifth Street.
·
Weather permitting, crews will pave Third Street starting Monday and continue work between Second Street and Fifth Street during 10-hour days Monday through Thursday.
Project Design
See Design Presentation for Detail
Fifth Street has been repaved in time for Saturday's Bike MS: City to Shore Ride fundraiser.
Concrete work is in progress on Sixth Street.