Work continues on the drainage project to alleviate flooding in the north end neighborhoods.

  • News

Work to be completed during the week of Nov. 19-23:

  • Feriozzi Concrete will finish work on Seventh Street between West Avenue and Bay Avenue, restoring curb, gutter and sidewalks. The contractor also will continue restoration on Haven Avenue between Seventh Street and Eighth Street, as well as Moore Avenue between Seventh and Eighth. 
  • Pipe crews will finish work between First Street and Second Street on West Avenue installing a main. At the same time, a second crew will continue installing a main on Bay Avenue between Second Street and Third Street.
  • Sodding will continue on Fourth and Fifth streets. 
Project design: See Design Presentation for Detail Work continues on the drainage project to alleviate flooding in the north end neighborhoods.
STEWARTVILLE

JERSEY SHORE WEEKEND

LATEST NEWS

Events

November

S M T W T F S
27 28 29 30 31 1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30

To Submit an Event Sign in first

Today's Events

No calendar events have been scheduled for today.