Trusted Local News

North End Neighborhood Drainage Project Update

NE Drainage Project work in progress on 3rd Street between West and Bay.

  • News

Work Expected for the Week of July 20-27   

  • Concrete crews will be finishing work on Fourth Street between West and Bay, restoring curb gutter and sidewalks. They will begin restoration on Simpson Avenue between Third and Fourth, while also starting restoration along Third Street from West to Bay.
  • Pipe crews will finish installing inlets and main on Third Street and Fifth Street, while continuing work on Sixth Street.
  • South State will finish base paving West Avenue between Fifth Street and Sixth Street on July 20. They will then mill and pave 2nd street from West to Bay; and Haven and Simpson Avenues from First to Third.
Project Design (Updated 1:43 p.m. July 20, 2018)