North End Neighborhood Drainage Project Update

Pictured: 3rd Street and Bay Avenue - New bulkhead in process.

  • News

WORK TO BE COMPLETED IN THE WEEK OF DEC. 24 TO 28

  • Feriozzi Concrete will finish work on Pleasure Avenue between Sixth Street and Seventh Street, as well as Sixth Street from Bay Avenue to the bulkhead. They will then begin work on the east side of Bay Avenue starting at Second Street.
  • Pipe crews will be installing 15" force main on 6th street from Bay ave to the bulkhead. A second crew will continue the installation of the pump station at 6th and Bay.
  • South State will continue paving Wednesday, Dec. 26. They will be topping Third Street and Seventh Street from West to Bay, as well as Moore and Haven between 7th and 8th.
  • Arthur Henry will continue the installation of the bulkhead at Third Street.
STEWARTVILLE

JERSEY SHORE WEEKEND

LATEST NEWS

Events

December

S M T W T F S
24 25 26 27 28 29 30
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31 1 2 3 4

To Submit an Event Sign in first

Today's Events

No calendar events have been scheduled for today.