DATE: Sunday, May 3
A couple takes advantage of warm weather and rebuilt beaches at 42nd Street on Sunday, May 3.
PROGRESS: By Sunday afternoon, little forward progress since Saturday was visible in the south end beach replenishment project, and the dredge Liberty Island did not appear to be at sea. From a feeder pipeline that lands just south of 42nd Street, the pipeline now extends southward, and beaches at 43rd and 44th Streets are closed. The work area extends to 44th Street.
WHAT’S NEXT: The project will proceed to 49th Street (anticipated to be complete by mid-May), 55th to 49th (mid-May to mid-June), 55th to 59th (mid-June to mid-July).