As of Tuesday morning (Aug. 25), the south end beach replenishment project area was just shy of 48th Street as it moves northward toward 47th Street.
Check OCNJ Daily for updates and photos of the Ocean City beach replenishment project for 2015 in the south end between 37th and 59th Streets.
DATE: Tuesday, August 25
PROGRESS: As of Tuesday morning, the project area had reached just south of the 48th Street beach entrance, which remained open. The beach entrances at 49th and 50th streets remained closed.
The work is advancing northward to 47th Street, where the third phase of work will end.
Work on the project resumed Aug. 13 after an 11-week delay for dredge repairs. The beaches between 37th Street and 47th Street are complete, as are the beaches between 55th Street and 51st Street.
WHAT’S NEXT: The project area will move to 55th Street to 59th Street for the final phase, which is expected to be complete by mid- to late-September.
READ MORE: Ocean City NJ Beach Replenishment 2015 Daily Update
FOR DAILY UPDATES by E-MAIL: Sign up for free