North End Neighborhood Drainage Project Update

Construction at the intersection of Second Street and Bay Avenue is part of the drainage project.

  • News

Work to be completed in the week of Jan. 7-11:

·   Feriozzi Concrete will continue work on the east side of Bay Avenue, working between Third Street and Sixth Street. 
·   Pipe crews will install a 15-inch force main on Fifth Street from Bay Avenue to the bulkhead. A second crew will continue the installation of the pump station at Sixth and Bay.  Project Design: See Design Presentation for Detail