Trusted Local News

North End Neighborhood Drainage Project Update

Continued improvements to infrastructure was an important issue in the campaign.

  • News
Work to be completed in the week of Feb. 25 to March 1:
  • Feriozzi Concrete will continue construction on both the east and west sides of Bay Avenue, working between 5th Street and 6th Street.
  • Lafayette will work on the pumping station in the 200 block of Bay Avenue. They also will begin the check valve chamber at 3rd Street and Bay Avenue.
  • Delta Line Construction will install the electrical hookups from the service poles to the pumping stations at all pumping station locations.