Work to be completed in the week of Oct. 29-Nov. 2:
Feriozzi Concrete will continue work on Seventh Street between West Avenue and Bay Avenue, restoring curbs, gutters and sidewalks. Asphalt crews will be starting early next week to pave alleyways and parking lots between Second Street and Sixth Street. They also will be paving the intersection of Fourth Street and West Avenue, Sixth Street between West and Bay, and the 600 blocks of Simpson Avenue and Haven Avenue.