North End Neighborhood Drainage Project

WORK TO BE COMPLETED IN THE WEEK OF DEC. 3 TO 7

  • Feriozzi Concrete will be finishing work on Moore Avenue between 7th Street and 8th Street. They will then begin work on Pleasure Avenue starting at 8th Street and working toward 6th Street.
  • Pipe crews will be finishing work between 2nd Street and 3rd Street on Bay Avenue installing 24-inch pipeline. They will then begin work between 5th Street and 6th Street on Bay Avenue, installing 24-inch pipeline.
  • South State will begin paving by the end of next week. They will be topping 3rd Street, then milling and paving 7th street from West to Bay, as well as Moore and Haven between 7th and 8th.
7th & Moore Ave is on track for paving.

Project Design

See Design Presentation for Detail

STEWARTVILLE

JERSEY SHORE WEEKEND

LATEST NEWS

Events

September

S M T W T F S
25 26 27 28 29 30 31
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 1 2 3 4 5

To Submit an Event Sign in first

Today's Events

No calendar events have been scheduled for today.