Looking north, drainage construction continues on Bay Avenue near Third Street.
Work to be completed in the week of Dec. 31 to Jan. 4:
- Contractor Feriozzi Concrete will continue construction on the east side of Bay Avenue, working between Second Street and Fourth Street.
- Pipe crews will install a 15-inch force main on Fifth Street from Bay Avenue to the bulkhead. A second crew will continue the installation of the pump station at Sixth Street and Bay.
- Another contractor, Arthur Henry, will continue the installation of the bulkhead at Third Street.
Project Design:
See Design Presentation for Detail