Trusted Local News

North End Neighborhood Drainage Project Update

Paving is scheduled for the intersection of Seven Street and Moore Avenue.

  • News

Work to be completed in the week of Dec. 17-21:

  • Construction contractor Feriozzi Concrete will continue work on Pleasure Avenue between Sixth Street and Seventh Street, as well as Sixth Street from Bay Avenue to the bulkhead. 
  • Pipe crews will install inlets on Pleasure Avenue before finishing tie-ins at both Third Street and Bay Avenue and at Sixth Street and Bay Avenue. A second crew will begin installation of the pump station at Sixth and Bay. 
  • Road contractor South State will begin work early next week. The contractor will be topping Third Street, milling and paving Seventh Street from West to Bay, as well as Moore and Haven avenues between Seventh and Eighth.
  • Another contractor, Arthur Henry, will continue the installation of the bulkhead at Third Street. 
Project Design: See Design Presentation for Detail Paving is scheduled for the intersection of Seventh Street and Moore Avenue.
STEWARTVILLE

JERSEY SHORE WEEKEND

LATEST NEWS

Events

November

S M T W T F S
27 28 29 30 31 1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30

To Submit an Event Sign in first

Today's Events

No calendar events have been scheduled for today.