Dear Friends:
A few brief project updates:
- Back Bay / Lagoon Dredging: We are currently out to bid to remove material from CDF 83 so that dredging can begin on July 1, 2015.
- Bay Avenue – 6th to 18th Streets (County Project): Concrete and drainage work is complete. Remaining paving will be undertaken when weather permits.
- North End Paving / Drainage: West Station Rd., Sindia Rd. Warwick Road, Haven Ave., North Street, First St. and adjacent alleys: Concrete work currently under construction. Paving to follow.
- Boardwalk Replacement Project – Phase 2: Nearing completion. Railing currently being reinstalled. Should be open within two weeks weather permitting.
- North End Pump Station and Paving: Awaiting permits.
This week we established a web page for updates on the south end beach replenishment project. You can view this information at:
www.ocnj.us/beachfill.
The administration is finalizing our recommended 2015 operating budget. I will be presenting the budget to the City Council at their meeting on February 12, 2015.
Have a great weekend!
Warm regards,
Jay A. Gillian