Check OCNJ Daily for updates and photos of the Ocean City beach replenishment project for 2015 in the south end between 37th and 59th Streets.
DATE: Thursday, August 20
PROGRESS: As of 2 p.m. Thursday, the beach is closed at 50th Street and 51st Street. Work to touch up the area between 52nd Street and 55th Street is complete. The pipeline now extends to a point midway between 50th and 51st Streets.
Work on the project resumed Thursday (Aug. 13) after an 11-week delay for dredge repairs. The beaches between 37th Street and 47th Street are complete.
WHAT’S NEXT: The project will proceed from 51st Street to 47th Street, then from 55th to 59th (by late September).
READ MORE: Ocean City NJ Beach Replenishment 2015 Daily Update
FOR DAILY UPDATES by E-MAIL: Sign up for free