Road and drainage projects are among big-ticket items in the funding package.

Work to be completed in the week of Feb. 18-22:

  • Feriozzi Concrete will continue construction on both the east and west side of Bay Avenue, working between 5th and 6th streets. 
  • Lafayette will be working on the pump station in the 200 block of Bay Avenue as well as the pump station in the 500 block of Bay.

Project Design:

See Design Presentation for Detail