Beach Replenishment Update: Work Reaches 51st Street

1648
SHARE
Sand-pumping at 51st Street in Ocean City, NJ on Friday, May 29.

Check OCNJ Daily for updates and photos of the Ocean City beach replenishment project for 2015 in the south end between 37th and 59th Streets.

DATE: Friday, May 29

PROGRESS: As of Friday evening, sand-pumping was going full speed at 51st Street. The beach at 51st and 52nd streets is closed.

The first two phases of the project (from 42nd Street to 37th Street, then from 42nd Street to 47th Street) are complete.

WHAT’S NEXT: The project will proceed from 52nd Street to 47th Street (by mid-June), then from 55th to 59th (mid-June to mid-July).