Home Latest Stories Bay Avenue Construction Update

Bay Avenue Construction Update

2274
SHARE
Detour signs were a common sight on Bay Avenue during construction.

During the past week, the contractor has commissioned the air release chambers that have been installed and continued work on the pipe connections at the new valve vault at the Cape May County Municipal Utilities Authority’s 20th Street Pump Station.

Also, the contractor has re-excavated the tie-in pits that are located at the north and south ends of the project at 8th Street and 31st Street, and has begun filling the new 20-inch PVC pipe full of water in anticipation of pressure testing and the transfer of flows to the new pipe.

By the end of work on Friday, Bay Avenue was open to two lanes of traffic, except between 8th and 9th streets. Due to the tie-in pit at this location, only the northbound lane of Bay Avenue will be open. Also, 31st Street will be completely closed between Simpson and Haven Avenues due to the tie-in pit at that location.

This coming week, it is expected that pressure testing and the transfer of flows will be completed. At that time, the slip-lining phase of the project will begin. With the exception of the 31st Street location and intermittently at 8th Street, no traffic shutdowns are anticipated. All other traffic control will be done through lane shifts and local detours.

The slip-lining phase of the project is expected to extend to mid to late-June. During this phase, traffic control should be done by lane shifts or limited local detours.

See full project update