Home Beach Replenishment Update Ocean City Beach Replenishment Update: April 14

Ocean City Beach Replenishment Update: April 14

2244
SHARE
An Army Corps of Engineers contractor is staging equipment on the beach at 34th Street. It will be transported down the beach to the start of the beach replenishment project area just south of 42nd Street in Ocean City NJ.

 

April 14

Ocean City NJ beach replenishment 2015 updates will be provided each day through the course of the project at the south end of Ocean City from 36th Street to 59th Street.

Today’s update is a fact sheet provided by the City of Ocean City on the project, which is expected to start Thursday, April 16 just south of 42nd Street.

 

FACT SHEET: OCEAN CITY BEACH REPLENISHMENT 2015 PROJECT IN SOUTH END OF OCEAN CITY, NJ

Project Description: Ocean City will receive approximately 1.6 million cubic yards of sand on approximately 2.6 miles of beach from 36th Street to 59th Street. Ancillary work includes the construction of pedestrian crossovers and the installation of new dune fence and dune grass. Our neighboring communities , Strathmere and Sea Isle, will also be receiving beach replenishment projects simultaneous with the work in Ocean City. The project is being overseen by the United States Army Corps of Engineers and is 100 percent federally funded at a total cost of $ 57 million. There is no local funding towards this project.

Ocean City NJ Beach Replenishment 2015
Sections of pipeline are now stacked on the beach at 43rd Street in Ocean City, a half-block south of where the feeder pipe lands on the beach.

Contractor: Great Lakes Dredge and Dock Company of Oak Brook, Illinois. They are the largest dredging operator in North America and have completed large scale dredging projects around the world.

The Dredge: The sand will be supplied by a hopper dredge named the “Liberty Island.” The sand will be gathered from a borrow area located approximately 2.5 miles offshore of Strathmere. The dredge will then transport the sand close to shore at one of two landing areas where it will then be pumped onto the beach. The first landing area is near 43rd Street and the second landing area is near 55th Street.

Schedule: The contractor has recently begun mobilization in Ocean City. The current project schedule calls for dredging operations to begin on April 16th and be completed in early July, with equipment demobilization to follow. Dredging operations will take place on a 24 hour / 7 day per week basis. Dates may vary and are dependent on weather, equipment and other factors. (See further project details below.)

 

FREQUENTLY ASKED QUESTIONS

Will the beach be closed for the project?

No more than 1,000 feet of beach will be closed at any one time. The closed area will shift north or south as the project proceeds. Beaches adjacent to the closed area will be open as normal. Some areas outside of the closed area may have a pipe running parallel to the ocean. Ramps will be constructed over the pipe at each street end and these beaches can be enjoyed as normal.

When and where will the project begin and how will it proceed?

Beachfill operations are expected to begin around April 16th and end around July 7th. The project will proceed as follows:

  • The first pipe landing will be located between 42nd and 43rd Streets:
    • The contractor will pump north from 42nd/43rd Streets to 36rh Street. (mid April – late April)
    • The contractor will then pump south from 42nd/43rd Streets to 49th (Late April – early May)
  • The second pipe landing will be located near 55th Street:
    • The contractor will pump north from 55th Street to 49th (early May – early June
    • Contractor will then pump south from 55th Street to 59th (early June – early July)

When will my beach be closed?

At this time it is not possible to estimate exactly when any one particular beach will be closed. Once the project begins and proceeds it may be possible to estimate what beaches will be affected for a relatively short duration of time on a day-to-day basis.

Ocean City NJ Beach Replenishment 2015
The Great Lakes Dredge and Dock Company has a $57.6 million contract to rebuild beaches and dunes in southern Ocean City, Strathmere and Sea Isle City.

Why is this work being done during the summer season?

The project is under the control of the Army Corps, and just one of several scheduled up and down the coast as a result of Superstorm Sandy. Ocean City has attempted to have the south end of the island included in the federal beach replenishment program since the 1980’s. It now is and will be replenished on a three year cycle moving forward. While the timing is not ideal, it will allow for the project to be completed prior to the height of the hurricane season and the winter storm season. While everyone will enjoy bigger and better beaches, the project is really about protecting billions of dollars of public and private property from future storm damage. It simply would not be responsible for Ocean City to decline this project because of its timing. The City will work very closely with the Army Corps and the contractor to minimize any inconvenience.

What will Ocean City do to minimize the inconvenience for residents and guests?

The City will be providing free shuttle service from the closed area to adjacent beaches that are open.  The shuttle service will tentatively begin on Memorial Day Weekend.

 

Ocean City NJ Beach Replenishment 2015 Update Archive and Links