WORK TO BE COMPLETED IN THE WEEK OF SEPT. 10 TO 14:
- Feriozzi Concrete will continue work on 5th Street between West Avenue and Bay Avenue, restoring curb gutter and sidewalks. A crew also will complete property restorations on 3rd Street.
- Pipe crews will continue installing main on 7th Street, working from Bay Avenue to West Avenue.
Project Design: