North End Neighborhood Drainage Project Update

North End Neighborhood Drainage Project Update

403
SHARE
A "Road Closed" sign on Bay Avenue at Second Street directs traffic away from the construction work.

Work to be completed in the week of Jan. 14 to 18:

  • Feriozzi Concrete will continue work on the east side of Bay Avenue, working between Fourth Street and Fifth Street. They also will work on the west side of Bay Avenue between Second Street and Fourth Street.
  • Pipe crews will install a 15-inch force main on Sixth Street from Bay Avenue to the bulkhead. They will also continue work on the pump station in the 500 block of Bay Avenue.

Project Design:

See Design Presentation for Detail